Cases
Excellence in VPSA & PSA Gas Separation
Beijing Peking University Pioneer Technology Corporation Ltd. (PKU PIONEER) specializes in innovative gas separation and energy-saving solutions since 1999.
Cases
Beijing Peking University Pioneer Technology Corporation Ltd. (PKU PIONEER) specializes in innovative gas separation and energy-saving solutions since 1999.

PKU Pioneer successfully commissioned a 3,000 Nm³/h VPSA oxygen plant for Double A in Thailand on October 3, 2026, delivering 93% purity oxygen—the third project with the repeat customer. The plant is designed to provide on-site oxygen for the pulp bleaching process, supporting Double A’s pulp and paper production. PKU Pioneer supported Double A in cost analysis and solution selection, and responded promptly during commissioning, ensuring a smooth test run and successful start-up. The on-schedule delivery reflects Double A’s continued confidence in PKU Pioneer’s VPSA technology and engineering capabilities.

A 15,000 Nm³/h VPSA oxygen plant, retrofitted within the existing facility to double capacity, now operational at a North China cast iron producer — achieving power consumption as low as 0.28 kWh/Nm³ (100% O₂ basis) and cutting oxygen costs by ~50% versus cryogenic separation, with a projected payback period of under one year.

A 13,000-Nm³/h VPSA oxygen system from PKU Pioneer is now operating in a Southeast Asian steel work, cutting oxygen production power use by 57% versus cryogenic separation and slashing annual electricity spend.

PKU Pioneer successfully commissioned a 12,500 Nm³/h VPSA oxygen plant for Wuxin Copper, helping eliminate oxygen supply bottlenecks and improve oxygen-enriched smelting efficiency. The project significantly reduced oxygen production costs, enhanced automation capabilities, and supported the customer’s capacity expansion and green metallurgy upgrade.

PKU Pioneer successfully commissioned a second-phase 14,000 Nm³/h PSA oxygen plant for Chifeng Yuanlian Iron & Steel, expanding total oxygen generation capacity to 28,000 Nm³/h. The project significantly reduced oxygen production costs, improved operational flexibility, and supported the steel mill’s energy-saving and low-carbon transformation goals.

PKU Pioneer successfully commissioned a 12,500 Nm³/h VPSA oxygen plant for Changjiang Steel, helping reduce liquid oxygen dependence and significantly lower blast furnace oxygen enrichment costs. The project was completed in just 73 days and delivers daily savings exceeding $14,285, further strengthening energy efficiency and cost competitiveness for large-scale steel production.

PKU Pioneer successfully commissioned two 5,556 Nm³/h VPSA oxygen plants for Jinchuan Group, providing stable oxygen supply for nickel flash smelting and copper synthesis furnaces. The project was completed ahead of schedule, helping the customer rapidly expand production capacity while improving oxygen supply flexibility, energy efficiency, and operational reliability.
Tell us about your project. We'll respond within 24 hours — no obligation.

Born from Peking University. 25+ years of innovation in industrial gas generation, serving 20+ countries worldwide.
Hi! I am here to help you find the right solution for your project.
You can share your product, capacity, or project needs. Our specialist will help you work out the next step.
Would you like a quick answer? Tap below to speak directly with our specialist on WhatsApp.
Opens WhatsApp. You choose what to send.